Spent 4 hours leveling my container foundation because I eyeballed it
I figured I could save some cash by just leveling the gravel pad myself instead of renting a laser level. Wound up with one corner a full 2 inches off after getting the first container dropped. Took me all Saturday with a bottle jack and shims to get it right. Anyone else try to skip a step and pay for it way worse later?
2 comments
Log in to join the discussion
Log In2 Comments
reeseanderson10d ago
Eric, you nailed it about the stake and string line. I did the same thing with a shed foundation once. What finally worked for me was using a long 2x4 and a basic 4-foot level. I laid it across the gravel pad in a grid pattern and kept adding or removing gravel until it was dead flat. Took an extra hour but saved me from the bottle jack headache you had.
8
ericjackson10d ago
You said "eyeballed it" and that tells me everything. The real issue isn't the leveling itself but that you skipped checking the ground before the container arrived. A quick stake and string line test would have caught that 2 inch gap before you had steel on site.
5