Burned 2 weeks rebuilding a schedule because I trusted my own bar chart instead of the crew
Back in 2019 I was running a 60 unit apartment job outside Fort Worth, and I spent two weeks redoing the whole schedule because I kept building my bar charts off the paper updates the super handed me. A concrete sub named Ray finally asked why his pour dates kept sliding when his guys were standing around ready, and that's when I saw it. He pulled up his own log on his phone and showed me the forms went in 3 days ahead of what my chart said. I had been treating the schedule like the truth instead of walking the site and asking the guys doing the work. Now I do a 10 minute loop with each foreman on Wednesday afternoons. How are you all handling field updates when the super and the subs tell two different stories?